Construction principles
-
- Core sequence: Installing columns (with wall braces) -> Column braces -> Trusses. Start installing from the space with wind braces and use temporary braces to position the clink
-
- Before roofing: Frames and purlins must be aligned, cleaned, and completely painted.
-
- Roofing & moving rules: Must use chalk/string to straighten the corrugated iron. When walking, the foot must be placed on the sound wave (lower wave); absolutely do not step on high waves and bright corrugated iron to avoid leakage.
Assembly process
1. Structural Erection Works
1.1 Installation of Anchor Bolts, Expansion Bolts, Chemical Anchor Bolts & Connection Bolts
1.2 Installation of Steel Columns
1.3 Installation of Rafters
1.4 Installation of Floor Beams / Joists
1.5 Installation of Steel Deck Floor (Decking)
1.6 Installation of Crane Beams
1.7 Installation of Column and Roof Diagonal Bracing
1.8 Installation of Longitudinal Bracing
1.9 Installation of Portal Frame Bracing
1.10 Installation of Roof Purlins, Anti-Roll Bracing and Purlin Tie Rods
1.11 Installation of Wall Girts, Anti-Roll Bracing and Girt Tie Rods
1.12 Installation of Panel Supporting Box Framing
1.13 Installation of Skylights / Roof Vents
1.14 Installation of Canopy
1.15 Installation of Steel Stairs and Handrails
1.16 Field Welding Works
2. Cladding Works
2.1 Installation of Roof Sheeting (Various Types of Roof Panels)
2.2 Installation of Wall Cladding / Wall Sheeting
2.3 Installation of Ridge Flashing
2.4 Installation of Roof Skylights
2.5 Installation of Gutters and Downspouts
2.6 Installation of Canopy Roof Sheeting
2.7 Installation of All Types of Doors
3. Warranty and Technical Support Works
4. Occupational Safety Works / Safety Works